Create a Construction Work Package (CWP)

  1. From your project's home page, navigate to the Work packaging module.

  2. Click on the Action menu and select Configure CWA and project values from the drop-down list.

  3. Click on the Add icon on the left toolbar and select Construction work package – CWP from the drop-down list.

  4. Construction work packages and installation work packages can also be created within the construction work areas, for example the North construction work area, by clicking on the North construction work area folder then select the add button.

  5. In the new dialog box, name your CWP. Work package names can be 100 characters in length.

  6. Note that the CWP name automatically begins with “CWP-“ by default. You can erase it.

  7. Click Add.

    Your created CWP will be located in the Unassociated packages folder by default when you create them outside of a construction work area folder.